Dates : 2022
Power : 15 kW
Service : Feasability study
Energy recovery study of two waterfalls in a fish plant
Energy recovery study of two waterfalls in a fish plant

Dates : 2022
Power : 800 kW
Service : Authorisation application file
Administrative file for the end of the concession period
Administrative file for the end of the concession period
Dates : 2022
Power : 120 kW
Service : Feasability study
Feasability study of an old mill with a subsidence of the sill since 2009
Feasability study of an old mill with a subsidence of the sill

Dates : 2021
Power : 90 kW
Service : Feasability study
Feasability study for the rehabilitation of an old mill
Feasability study for the rehabilitation of an old mill

Dates : 2022
Power : 350 kW
Service : Due diligence
Due diligence of existing power plants
Due diligence of existing power plants in France

Dates : 2022
Power : 70 kW
Service : Feasability study
Feasibility study for an old water mill in France
Feasibility study for an old water mill in France

Dates : 2020-2022
Power : 400 kW
Service : Complete project management
Design and commissioning of two off-grid hydropower plants in Papua New Guinea
Design and commissioning of two off-grid hydropower plants in Papua New Guinea

Dates : 2021-2022
Power : -
Service : Territorial scheme
Hydroelectric potential study and mapping of two povinces of Papua New Guinea.
Renewable energy resource mapping in Papua New Guinea

Dates : 2021
Power : 480 kW
Service : Potential study
Potential study for the refurbishment of a former hydropower plant
Potential study for the refurbishment of a former hydropower plant

Dates : 2022
Power : 500 kW
Service : Due diligence
Due diligence of an existing power plant in Jura mountain
Due diligence of an existing power plant in Jura mountain

Dates : 2020-2021
Power : 12 kW
Service : Feasability study
Water treatment plant outflow valorization study
Water treatment plant outflow valorization study

Dates : 2021
Power : 740 kW
Service : Due diligence
Due diligence of an existing power plant
Due diligence of an existing power plant in the south of France

Dates : 2021
Power : 500 kW
Service : Due diligence
Due diligence of a future power plant in the French Alps
Due diligence of a future power plant in the French Alps

Dates : 2021
Power : 163 kW
Service : Preliminary design study
Hydroelectric equipment of an existing weird
Hydroelectric equipment of an existing weird

Dates : 2021
Power : 43 kW
Service : Feasability study
Rehabilitation of a former mill on the Morge river in France
Rehabilitation of a former mill on the Morge river in France

Dates : 2021
Power : 140 kW
Service : Feasability study
Reclamation of a former mill for electrical self-consumption
Reclamation of a former mill for electrical self-consumption

Dates : 2021
Power : 20 kW
Service : Feasability study
Pre feasibility study for the reclamation of a former sawmill
Pre feasibility study for the reclamation of a former sawmill

Dates : 2021
Power : 370 kW
Service : Feasability study
Refurbishment of two former hydroelectric power plants on the Morge and authorization application file
Refurbishment of two former hydroelectric power plants on the Morge

Dates : 2021
Power : 500 kW
Service : Due diligence
Due diligence – Saint-Génix hydropower plant
Due diligence – Saint-Génix hydropower plant
Dates : 2021
Power : 22 kW
Service : Feasability study
Feasibility study for the rehabilitation of an old power plant
Feasibility study for the rehabilitation of an old power plant
Dates : 2021
Power : 45 kW
Service : Feasability study
Feasability study for the rehabilitation of an old mill
Feasability study for the rehabilitation of an old mill

Dates : 2021
Power : 15-46 kW
Service : Feasability study
Reclamation of a former sawmill for the production of electricity
Reclamation of a former sawmill for the production of electricity

Dates : 2021
Power : 1090 kW
Service : Due diligence
Due diligence of an existing power plant in France
Due diligence of an existing power plant in France

Dates : 2020-2021
Power : 1600 kW
Service : Feasability study
Expertise of a hydroelectric power plant on Arve river
Expertise of a hydroelectric power plant on Arve river

Dates : 2020
Power : 60 kW
Service : Feasability study
Feasability study for the rahabilitation of an old mill
Feasability study for the rahabilitation of an old mill

Dates : 2020
Power : 52 kW
Service : Feasability study
Feasability study for an old mill
Feasability study for an old mill

Dates : 2019
Power : 2800 kW
Service : Preliminary design study
Installation of underground Francis turbines
Installation of underground Francis turbines

Dates : 2019-2020
Power : 2000 kW
Service : Preliminary design study
Best use of irrigation canal available power
Best use of irrigation canal available power
Dates : 2019-2020
Power : 4500 kW
Service : Detail design study
Detailed design studies of 2 new medium head projects
Detailed design studies of 2 new medium head projects

Dates : 2020
Power : 2 200 kW
Service : Feasability study
Study of the hydroelectric potential of different weir on the Yonne river in Auxerre and his suburbs
Study of the hydroelectric potential of different weir in Bourgogne

Dates : 2020
Power : 300 kW
Service : Feasibility study
Feasability study for two old mill on the Yonne river
Feasability study for two old mill on the Yonne river

Dates : 2019
Power : 15 kW
Service : Preliminary design study
Turbining a minimum flow with a second-hand hydraulic turbine
Turbining a minimum flow with a second-hand hydraulic turbine

Dates : 2019
Power : 500 kW
Service : Feasibility study
Faisability study for the hydroelectric equipment of an existing weir downtown
Faisability study for the hydroelectric equipment of an existing weir downtown
Dates : 2020
Power : 15 kW
Service : Feasibility study
Pre-faisability for the rehabilitation of an old mill
Pre-faisability for the rehabilitation of an old mill

Dates : 2020
Power : 500 kW
Service : Preliminary design study
Design study of a new medium head hydro scheme in the Vosges
Design study of a new medium head hydro scheme in the Vosges

Dates : 2020
Power : 100 kW
Service : Authorisation application file
Assistance to complete the application files for two new hydro plants
Assistance to complete the application files for two new hydro plants

Dates : 2019
Power : 1000 kW
Service : Feasibility study
Legal recognition of the water rights for six old mills
Legal recognition of the water rights for six old mills
Dates : 2020
Power : 1000 kW
Service : Preliminary design study
Refurbishment of a 1’000 kW low-head hydroelectric scheme
Refurbishment of a 1’000 kW low-head hydroelectric scheme

Dates : 2019
Power : 53 kW
Service : Feasibility study
Refurbishment of two old hydroelectric schemes on the Orain river
Refurbishment of two old hydroelectric schemes on the Orain river

Dates : 2019
Power : 397 kW
Service : Feasibility study
Legal recognition of the water rights for three old mills
Legal recognition of the water rights for three old mills
Dates : 2018-2019
Power : 600 MW
Service : Due diligence
Technical specification of a 600 MW pumped-storage scheme
Technical specification of a 600 MW pumped-storage scheme

Dates : 2019
Power : 5 000 kW
Service : Feasibility study
Discharge measurement of two mountain stream located in the French Alps (annual average discharge between 2.5 and 3.5 m3/s)
Discharge measurement of two mountain stream located in the French Alps

Dates : 2019
Power : 10 000 kW
Service : Due diligence
Due diligence of 14 hydroelectric schemes in French West Indies, with a total installed capacity of more than 10 MW
Due diligence of 14 hydroelectric schemes in French West Indies

Dates : 2019
Power : 50 kW
Service : Feasibility study
Rehabilitation of an old water mill
Rehabilitation of a 50 kW old water mill in western part of France

Dates : 2018-2019
Power : 30 - 160 kW
Service : Territorial development scheme
Study of the hydroelectric potential of the Somme river in the north of France
Study of the hydroelectric potential of the Somme river in the north of France

Dates : 2018-2019
Power : 124 000 kW
Service : Due diligence
Expertise of the model and prototype efficiency hills of 2×62 MW Kaplan turbines
Expertise of the model and prototype efficiency hills of 2×62 MW Kaplan turbines

Dates : 2018-2019
Power : 130 kW
Service : Due diligence
Due diligence of a 130 kW scheme located on an old irrigation canal
Due diligence of a 130 kW scheme located on an old irrigation canal

Dates : 2018
Power : 960 kW
Service : Preliminary design study
Analysis of various turbine types for the Arves river near Geneva
Analysis of various turbine types for the Arves river near Geneva

Dates : 2018-2019
Power : 180 kW
Service : Feasibility study
Rehabilitation of an old hydroelectric scheeme on a mountain stream
Rehabilitation of an old hydroelectric scheme on a mountain stream

Dates : 2018-2019
Power : 1 100 kW
Service : Preliminary design study
Design study of 2 new high head hydroelectric schemes in the Alps
Design study of 2 new high head hydroelectric schemes in the Alps
Dates : 2018-2019
Power : 4240 kW
Service : Preliminary design study
Preliminary design studies of three high head hydro projects in the French Alps
Preliminary design studies of three high head hydro projects in the French Alps

Dates : 2018
Power : 5 - 80 kW
Service : Territorial development scheme
Study of the hydroelectric potential of the territory of Saint-Etienne Métropole
Study of the hydroelectric potential of Saint-Etienne Métropole

Dates : 2018
Power : 450 kW
Service : Assistance to the owner
Assistance to the owner for an hydropower plant on drinkig water system
Assistance to the owner for an hydropower plant on drinkig water system

Dates : 2018
Power : 20 kW
Service : Feasibility study
Rehabilitation of two old mills in the Jura Mountains
Rehabilitation of two old mills in the Jura Mountains

Dates : 2018-2019
Power : 270 kW
Service : Feasibility study
Feasibility study for the rehabilitation of six hydropower plant
Feasibility study for the rehabilitation of six hydropower plant

Dates : 2018
Power : 60 kW
Service : Feasibility study
Feasibility study for the rehabilitation of an old sawmill on the Ognon river under 1.50 m head.
Feasibility study for the rehabilitation of an old power plant
Dates : 2018
Power : 1 000 kW
Service : Due diligence
Offer stage design technical advisor
Due diligence of a tender proposal for an international project

Dates : 2018
Power : 30 kW
Service : Feasibility study
Refurbishment of an old hydroelectric scheme on the Sèvre Nantaise river
Refurbishment of an old hydroelectric scheme on the Sèvre Nantaise river

Dates : 2017
Power : 45 kW
Service : Feasibility study
Refurbishment of an old hydro power plant on the Volane river
Refurbishment of an old hydro power plant on the Volane river
Dates : 2017-2018
Power : 500 kW
Service : Owner's engineering
Technical assistante to the project owner to issue the complete water right demand
Construction of a new 500 kW hydroelectric power plant in the Pyrénées mountains

Dates : 2018
Power : 2000 kW
Service : Due diligence
Detailed technical expertise of a 2 MW power plant equiped with 4 Francis turbines under a low head
Expertise / due diligence of a 2 MW power plant

Dates : 2018
Power : 2 000 kW
Service : Due diligence
Detailed due diligence of a 2 MW HEPP under 500 m head in Sao Tome-and-Principe
Expertise / due diligence of a 2 MW existing power plant

Dates : 2017
Power : 200 kW
Service : Feasibility study
Detailed feasibility study of the installation of various types of turbines on 7 drinking water distribution systems
Installation of turbines on several drinking water distribution systems

Dates : 2016 - 2017
Power : 2 000 kW
Service : Summary preliminary study
Detailed feasibility and design of a very old mill refurbishment
Detailed feasibility and design of an old mill refurbishment with brand new turbines

Dates : 2016 - 2017
Power : 400 kW
Service : Feasibility study
Technical support to the Owner in an EPC contract
EPC contrat analysis for the equipment of two low head weirs

Dates : 2017
Power : 300 kW
Service : Feasibility study
Detailed study of teh valorization of the discharge flow getting out of a 3 Pelton power
High head discharge flow valorization with a crossflow turbine

Dates : 2017
Power : 80 kW
Service : Feasibility study
Detailed feasibility of an old mill refurbishment
Refurbishment of an old hydroelectric scheme
Dates : 2017
Power : 7 200 kW
Service : Due diligence
Due diligence of 13 hydroelectric power plants
Due diligence of 13 small hydroelectric plants

Dates : 2016 - 2017
Power : 500 kW
Service : Feasibility study
Due diligence of 4 weir to be equiped with turbine
Due diligence of 4 low and medium head hydroelectric schemes

Dates : 2016 - 2017
Power : 350 kW
Service : Feasibility study
Feasibility study of the installation of Very Low Head (VLH) turbines vs. Kaplan turbines
Equipment of 2 m high spillway gates with 2 turbines

Dates : 2017
Power : 500 kW
Service : Feasibility study
Feasibility study of the installation of hydrodynamic screws vs. Kaplan turbines
Equipment of 2 m high 7 spillway gates with low head turbines

Dates : 2016
Power : 400 kW
Service : Feasibility study
Feasibility study of the installation of a Very Low Head (VLH) turbine
Equipment of 4 m high spillway gates with a turbine

Dates : 2016
Power : 20 kW
Service : Summary preliminary study
Technical detailed studies bound to the equipment of an existing discharge gate with a hydrodynamic screw
Installation of a hydrodynamic screw on an existing discharge gate
Dates : 2016 - 2017
Power : 150 kW
Service : Feasibility study
Detailed feasibility analysis of an old turbine
Rehabilitation of a low head turbine within an industrial site

Dates : 2016 - 2019
Power : 20 000 kW
Service : Complete project management
Owner’s engineering bound to the development of renewable energies in the whole Comoros islands area
Complete project management of the refurbishment and upgrade of an old plant

Dates : 2016 - 2018
Power : 70 kW
Service : Complete project management
Detailed design, tender documents and complete project management of the refurbishment and upgrade of an old low head plant
Complete project management of the refurbishment and upgrade of an old plant

Dates : 2016 - 2017
Power : 300 kW
Service : Feasibility study
Detailed studies of the rehabilitation and upgrade of a plant
Detailed feasibility of a plant rehabilitation of an old plant
Dates : 2016 - 2019
Power : 53 500 kW
Service : Work Execution Branch
Technical assistance and expertise related to the supply, erection and commissioning of 7 new hydropower plants in Africa
Transient and stability analysis, technical specification of 7 new hydropower plants

Dates : 2016 - 2017
Power : 130 kW
Service : Complete project management
Detailed design, tender documents and complete project management of the refurbishment and upgrade of an old low head plant
Complete project management of the refurbishment and upgrade of an old plant

Dates : 2016
Power : 530 kW
Service : Feasibility study
Comparison of two different optimization scenarios
Optimization of a power plant under operation
Dates : 2015 - 2016
Power : 500 kW
Service : Summary preliminary study
Detailed studies of three low head weirs rehabilitation an upgrade on the Doubs river, in urban area and protected zones
Rehabilitation of three low weirs on the Doubs river

Dates : 2015 - 2016
Power : 1 600 kW
Service : Summary preliminary study
Transient analysis of the penstock under various conditions
Improvement of the transient response of 3 Francis turbines

Dates : 2015
Power : 75 kW
Service : Feasibility study
Feasibility study of the rehabilitation of an old retired sawmill
Feassibility study for the refurbishment of an old sawmill

Dates : 2015
Power : 50 kW
Service : Feasibility study
Feasibility study of the equipment of a low head dam in a urban area
Feasibility study for a low head dam equipement

Dates : 2015 - 2016
Power : 2 300 kW
Service : Feasibility study
Deatailed feasibility study of the refurbishment, upgrade and optimization of two hydroelectric power plants
Detailed feasibility study for the complete optimization of two EDF’s plants

Dates : 2015 - 2016
Power : 40 kW
Service : Feasibility study
Comparison of technical and economical advantages and drawbacks of electricity delivery to the grid
Refurbishment of a combined electricity production and drinking water pumping

Dates : 2015
Power : 250 kW
Service : Feasibility study
Feasibility study of a site upgrade with very low head turbines
Old water mill upgrade with low head turbines

Dates : 2015
Power : 50 kW
Service : Feasibility study
Feasibility study of a rehabilitation and/or and upgrade of a horizontal Francis turbine
Feasibility study for the rehabilitation of an horizontal Francis turbine
Dates : 2015
Power : 2 000 kW
Service : Assistance to the Owner
Assistance to the dam/power plant owner for a contract negociation
Assistance for 4 VLH turbine suply contract negociation

Dates : 2015
Power : 25 000 kW
Service : Due diligence
Due diligence of 10 hydroelectric plants
Due diligence of 10 hydroelectric plants under low and medium head

Dates : 2016
Power : 10 000 kW
Service : Summary preliminary study
Detailed feasibility study incl. on site measurement campain, concept freeze, energy production and optimisation, technical aspects bound to isolated network
Detailed feasibility study for the construction of a new HEPP in Sierra Leone

Dates : 2015
Power : 55 kW
Service : Feasibility study
Feasibility study of an old water mill rehabilitation
Old hydroelectric plant refurbishment and modernization

Dates : 2015
Power : 110 kW
Service : Feasibility study
Feasibility study a very low head (1.40 m only) rehabilitation
Very low head hydroelectric scheme rehabilitation

Dates : 2014 - 2015
Power : 320 kW
Service : Complete project management
Technical assistance to selection of the manufacturer, manufacturing supervision, erection preparation and supervision, commissioning control
Technical assistance to the procurement, manufacturing and erection of a Kaplan

Dates : 2014 - 2016
Power : 2 500 kW
Service : Complete project management
Complete project management of the hydromechanical, electromechanical, electrical and SCADA system of a vertical Kaplan turbine rehabilitation
Complete project management of vertical Kaplan rehabilitation

Dates : 2014 - 2015
Power : 200 kW
Service : Complete project management
Detailed design, tender documents and complete project management of a new hydroelectric scheme in a urban area
Complete project management of “SAXO” vertical Kaplan construction

Dates : 2014
Power : 250 kW
Service : Summary preliminary study
Detailed feasibility study for the cosntruction of a new hydroelectric scheme
Detailed feasibility study of a crossflow turbine or Archimede screws

Dates : 2014
Power : 100 kW
Service : Feasibility study
Feasibility study of an old water mill rehabilitation
Feasibility study of a private water mill rehabilitation

Dates : 2014 - 2016
Power : 1 500 kW
Service : Complete project management
Detailed design, tender documents and complete project management of four Kaplan units rehabilitation and detailed design, tender documents and complete project management of the replacement of 2 old lock vanes
Complete project management of the réhabilitation of 4 Kaplan units

Dates : 2014
Power : 30 000 kW
Service : Due diligence
Due dilligence of four HEPP built between 1908 and 1974
Due diligences of 4 existing hydroelectric plants

Dates : 2014
Power : 205 000 kW
Service : Complete project management
Assistance to the dam/power plant owner for a contract negociation related to the upgrade of the five Kaplan turbines
Assistance for turbines refurbishment contract negociation

Dates : 2014
Power : 350 kW
Service : Summary preliminary study
Detailed feasibility study of the replacement of and old Francis turbine
Francis turbine replacement by a Kaplan, withmore than doubled nominal flowrate

Dates : 2014 - 2015
Power : 1 500 kW
Service : Complete project management
Detailed design, tender documents and complete project management of a 250 m hydroelectric scheme rehabilitation
Complete project management of the hydromechanical part for a rehabilitation

Dates : 2013
Power : 12 000 kW
Service : Summary preliminary study
Sizing and cost estimate of a new Pelton turbine replacing the old one under 600 m head
Detailed feasibility study of a Pelton turbine rehabilitation under 600 m head

Dates : 2013
Power : 150 kW
Service : Due diligence
Prefeasibility studies of various hydroelectric schemes in th Region of the upper French Alps
Pre-feasibility study of various hydro projects (refurbishment or plants for sale)

Dates : 2013
Power : 1 500 kW
Service : Summary preliminary study
Vibration analysis, start and stop tests, dynamic behavious analysis, detailed analysis of the energy production database
Hydromechanical and electrical equipment due dilligence

Dates : 2013
Power : 2 000 kW
Service : Feasibility study
Detailed feasibility study of the rehabilitation of a hydroelectric power plant built in the 1920’s
Detailed feasibility study of a hydroelectric power plant under operation

Dates : 2013
Power : 7 000 kW
Service : Summary preliminary study
Detailed Feasibility Study (DFS) of a new hydroelectric power plant in rural area of Uganda
Project of hydroelectric power plant in Uganda

Dates : 2013
Power : 44 000 kW
Service : Feasibility study
Complete feasibility study and financial optimisation of two new schemes
Two new projects of hydroelectric power plants in the upper part of Guinea

Dates : 2012 - 2014
Power : 50 kW
Service : File for the water right demand
Detailed feasibility study and constitution of the complete file for the water right demand
Detailed studies and assistance to the demand for the water right renewal

Dates : 2013
Power : 8 000 kW
Service : Summary preliminary study
Detailed feasibility study of various scenarios of Pelton turbine
Detailed feasibility study of a new high head scheme in the swiss Alps

Dates : 213
Power : 2 000 kW
Service : Feasibility study
Turbine sizing and budget estimate of new hydromechanical and electromechanical equipment of two old hydroelectric plant
Refurbishment of two hydroelectric plant on the Doubs river

Dates : 2013
Power : 30 kW
Service : Feasibility study
Detailed feasibility study of a small hydropower scheme
Water treatment plant outflow valorization study
Dates : 2012 - 2013
Power : 3 500 kW
Service : Feasibility study
Turbine sizing and technical specification for two new groups
Old hydroelectric plant refurbishment and modernization

Dates : 2012
Power : 250 kW
Service : Feasibility study
Hydromechanical and electromechanical equipment sizing for a new plant located on a discharge canal
Valorization of exhaust water flowrate from a Molybdenum plant

Dates : 2012 - 2013
Power : 2 500 kW
Service : Summary preliminary study
Due dilligence of an existing scheme equipped with 4 horizontal Pelton units
Feasibility study of the Montsapey scheme rehabilitation

Dates : 2012 - 2014
Power : 3 800 kW
Service : Complete project management
Detailed design, tender documents and complete project management of a high head (670 m) new hydroelectric scheme
Project management for electromechanical part of a high head scheme

Dates : 2012
Power : 2 050 kW
Service : Feasibility study
Due dilligence of 3 existing hydroelectric power plant
Storage hydropower plants refurbishment and upgrade
Dates : 2012 - 2014
Power : 218 000 kW
Service : Due diligence
Technical assistance to bidders to the renewal of the EDF/SHEM French hydroelectric concessions
Renewal of the EDF/SHEM French hydroelectric concessions
Dates : 2012 - 2014
Power : 37 000 kW
Service : Due diligence
Technical assistance to bidders to the renewal of the EDF/SHEM French hydroelectric concessions
Renewal of the EDF/SHEM French hydroelectric concessions
Dates : 2012 - 2014
Power : 359 000 kW
Service : Due diligence
Technical assistance to bidders to the renewal of the EDF/SHEM French hydroelectric concessions
Renewal of the EDF/SHEM French hydroelectric concessions
Dates : 2012
Power : 500 000 kW
Service : Due diligence
Review of Tender and suppliers bid for the supply, erection and commissioning
Tender documents of the High Grand Falls hydroelectric powerplant

Dates : 2011 - 2012
Power : 5 000 kW
Service : Summary preliminary study
Analysis of various optimization scenario within the context of the end of the current “concession” and technical part of the tender document and assistance to the plant owner for selecting an operator
Optimization study of the hydroelectric plant of Rophemel dam

Dates : 2011
Power : 250 kW
Service : Feasibility study
Detailed feasibility study for the refurbishment of two old Fontaine turbines
Refurbishment study of an old water mill on the Loir river
Dates : 2011 - 2012
Power : 3 500 kW
Service : Complete project management
Detailed design, tender documents and complete project management of a high head (530 m) new hydroelectric scheme
Project management for electromechanical part of a high head scheme

Dates : 2011
Power : 250 kW
Service : Feasibility study
Due diligence of an old site located on a mountain stream
Feasibility study of a hydroelectric scheme located on a mountain stream

Dates : 2011
Power : 100 kW
Service : Summary preliminary study
Feasibility study following a detailed tender issued by the ADEME
Rehabilitation of an old water mill, in a medium size city downtown

Dates : 2010 - 2011
Power : 100 kW
Service : Feasibility study
Feasibility study following a detailed tender issued by the ADEME
Water mill upgrade detailed feasibility study following a detailed tender

Dates : 2010
Power : 100 kW
Service : Feasibility study
Technical, environmental and legal assistance to the local energy trader
Overhaul feasibility study of four old mills and hydroelectric schemes
Dates : 2010
Power : 800 000 kW
Service : Due diligence
Pre-feasibility study of the major project in Congo-Brazzaville
Pre-feasibility study of the major project of Sounda on the Kouilou river
Dates : 2010
Power : 1 000 kW
Service : Feasibility study
Feasibility study of three hydroelectric schemes turbining the compensation water of existing EDF’s dams
Existing medium head dams amenity flow turbines study

Dates : 2010
Power : 50 kW
Service : Feasibility study
Refurbishment of an old water mill
Feasibility study of an old water mill in a very old building

Dates : 2010
Power : 10 kW
Service : Feasibility study
Refurbishment of an old and small hydroelectric plant (existing double Francis horizontal axis)
Feasibility study of a pico hydroelectric plant

Dates : 2009
Power : 1 000 kW
Service : Feasibility study
Feasibility study of building a wind farm to feed the energy demand of a water treatment plant (European FASEP project)
Feasibility study of building a wind farm in Philippines

Dates : 2009
Power : 250 kW
Service : Feasibility study
Maragondon’s river feasibility studies of hydroelectric plants
Maragondon’s river feasibility studies of hydroelectric plants

Dates : 2007
Power : 70 kW
Service : Feasibility study
Rehabilitation of a retired hydroelectric plant in an old sawmill
Refurbishment of an old retired hydroelectric plant