Hydroelectric feasibility study for the optimization of the Roche power plant

- France (39)
- 2024
- 566 kW
- Feasibility study
- The feasibility study aimed to determine the optimal scenario for optimizing the La Roche hydroelectric power plant on the Ain River. Currently, the plant is equipped with a turbine supplying energy to the grid under an H07 contract. With this contract nearing its end and the DDT requiring the compliance of the fish pass, the municipality decided to launch this study to harness the available flow rates and integrate a hydroelectric component with an environmental focus.