Pre-porject study and compilation of administrative documentation for the rehabilitation of an old power plant on the Bienne river

  • France (39)
  • 2022
  • 500 kW
  • Summary preliminary study
  • Pre-project development for the rehabilitation of an old industrial site according to 2 development scenarios. The first scenario was studied within the legal framework of the water rights based on the installation's established title, while the second scenario involved increasing the power capacity. Hydreole completed all stages of the pre-project (hydrology reconstruction, hydraulic studies of the bypassed section, design and costing of the development, production study).