Due diligence of 13 hydroelectric power plants, with installed power from 400 kW to 1200 kW: analysis of the past production, schemes numerical model building incl. the dam, canal, penstock, turbine, generator, and connection to the grid.

Due diligence of 13 small hydroelectric plants
France (08, 11, 12, 24, 43)
2017
7 200 kW
Feasibility study