Drawing up of the authorisation application file to increase the installed capacity of two existing hydropower plants. Analysis of several technical solutions to implement a fish ladder on the intake weir of one of the hydropower plants. The river creates a gorge difficult to access during the construction work but also in operation making every solution hard to implement and maintain.

Authorisation application file to increase the installed capacity of 2 existing hydropower plants in the French department of Jura
France (39)
2025-2026
406 kW et 395 kW
Authorisation application file