Design and commissioning of two off-grid hydropower plants in Papua New Guinea
Country : Papoua New Guinea
Dates : 2020-2022
Power : 400 kW
Service : Complete project management
Dates : 2020-2022
Power : 400 kW
Service : Complete project management
Hydrological survey, electricty demand assessment, analyses of the schemes’ location, design of the hydropower plant and its mini-grid. Cost estimate. Tender documents. Complete project management.